TCN starts restoration work of AFAM/IPP/ELELENWO 132 kV DC transmission line
From our correspondent
Port Harcourt (Core Reporters) The Transmission Company of Nigeria (TCN) is carrying out rehabilitation works on the four vandalized towers along the 132 kV Afam/IPP/Elelenwo double circuit transmission line, Core Reporters reports.
The affected towers, identified as T50, T51, T52 and T53, were surveyed on August 6, 2026 by TCN linemen. Further inspection revealed that critical bracing members had been removed from the towers, compromising the structural integrity of all four towers.
Following this, TCN has urgently mobilized a contractor to the site who will carry out the repairs. A formal handover ceremony was held by the Port Harcourt Transmission Region yesterday, Tuesday 8 September 2026 to celebrate the commencement of the rehabilitation works.
Speaking during the handover ceremony, the Lines Manager, Port Harcourt Transmission Region, Engr. Azuh Lucky, who represented TCN management, highlighted the need for greater community involvement in protecting transmission infrastructure.
He called on Elelenwo residents, their traditional rulers and the local government chairman to assist TCN citizens in the fight against vandals as the rehabilitation works progress. He stressed that continued community awareness and cooperation are essential to prevent further acts of vandalism.
We are aware of the risk that vandalism to these towers poses to the reliable transmission of electricity along the corridor. The Company will make every effort to ensure the timely completion of the rehabilitation works.
TCN appeals to residents of Elelenwo and surrounding communities to support ongoing rehabilitation efforts and remain vigilant against vandalism around broadcast facilities. Community cooperation is critical to safeguard restored infrastructure and ensure reliable power transmission along the line