TCN restores collapsed Kanji-Birnin Kebbi 330 kV transmission line





Deprecated: The WP_Dependencies->add_data() function was called with an argument i.e deprecated from version 6.9.0! IE conditional comments are ignored by all supported browsers. In /home/corerepo/public_html/wp-includes/functions.php online 6260























TCN restores collapsed Kanji-Birnin Kebbi 330 kV transmission line – Core Reporters















TCN restores collapsed Kanji-Birnin Kebbi 330 kV transmission line

From our journalist

Abuja (Core Reporters) The Transmission Company of Nigeria (TCN) has rehabilitated the 330 kV Kainji-Birnin Kebbi single circuit transmission line, which was mothballed following the collapse of Tower 367 on September 7, 2026.

TCN management said the line was restored at 5.24pm on Thursday 1 October 2026, following the erection of an Emergency Recovery System (ERS) tower at the tower’s location in Yauri.

According to management, the restoration work involved the dismantling and decommissioning of the collapsed tower, the alignment and preparation of the conductors and skywire, the construction of the ERS tower and the execution of other associated works necessary to restore the line safely.

“Our engineers worked around the clock to complete the works and bring the line back into service as quickly and safely as possible.

“We appreciate the patience and understanding of electricity consumers in the affected areas throughout the outage and remain committed to maintaining a stable and reliable transmission grid.” The TCN management stated this.

Top reporters

Check Also

66th anniversary of independence: With reforms, Tinubu laid solid foundation for Nigeria’s prosperity – Obasa

Speaker of the Lagos State House of Assembly, Rt. Hon. Mudashiru Ajayi Obasa, has said …

Leave a Reply

Your email address will not be published. Required fields are marked *